Project Updates

March 2019

  • Addendum #1 for the Design Build RFP was issued.  The Program Management team also provided written responses to queries raised during the Initial Design Concept meetings.
  • The Program Management team continues to evaluate and pursue additional potential Project grant funding opportunities.
  • Wet Well construction activities continue. The very wet February weather resulted in some slowdown of construction activity. The Program Manager anticipates “soil freezing” to be complete soon, followed by commencement of excavation activities.
  • SRWA continues to work on the EIR Addendum.
  • The Program Management team continues to coordinate easement and Right of Way agreements with affected landowners.
  • The SRWA General Manager is continuing his discussions with County staff regarding the finished water pipeline alignments and roadway restoration conditions.
  • The Program Management team continues to work on the SRF technical application package.

February 2019

  • Wet Well construction activities continue. Anticipate “soil freezing” to be complete by around mid-February, followed by commencement of excavation activities.
  • The SRWA PM team held Initial Design Concept meetings with each Design Build team.
  • SRWA continues to work on the EIR Addendum.
  • The Program Management team continues to coordinate easement and Right of Way agreements with affected landowners.
  • General Manager is continuing his discussions with County staff regarding the finished water pipeline alignments and roadway restoration conditions.
  • The Program Management team continues to work on the SRF technical application package.