Project Updates

December 2019

  • The SRWA successfully completed development and testing of the infiltration gallery.
  • The Wet Well contractor began the demobilization of the temporary pumping, piping, and settling basin facilities.
  • The SRWA Program Management (PM) team continues to negotiate the Design-Build Contract with Jacobs, the successful proposer.
  • The PM team continues to evaluate and pursue additional Project grant funding opportunities.
  • Coordination efforts for Right-of-Way acquisition continues.
  • The PM team coordinated and negotiated with Stanislaus County on encroachment permit conditions of approval and Aldrich Bridge design.
  • The PM team submitted a San Joaquin Fish Population Enhancement Program grant application for the Raw Water Pump Station and Raw Water Transmission Main.

November 2019

  • Final construction work was completed on the Wet Well in preparation for the infiltration gallery development and testing activities.
  • The SRWA Program Management (PM) team continues to negotiate the Design-Build Contract with Jacobs, the successful proposer.
  • The PM team continues to evaluate and pursue additional Project grant funding opportunities.
  • The PM team negotiated an encroachment permit with Stanislaus County.
  • Coordination efforts for Right-of-Way acquisition continues.
  • The PM team submitted the WaterSMART Drought Resiliency grant application for the Turlock Finished Water Transmission Main.