Project Updates

May 2019

  • Additional Addenda for the Design Build RFP were issued.  The Program Management team also provided responses to questions and requests for clarification and/or more information.
  • The Program Management team continues to evaluate and aggressively pursue additional potential Project grant funding opportunities.
  • Wet Well construction activities continue. The dryer weather in April allowed excavation activities to continue. We anticipate moving forward with construction of the initial concrete pours in May.
  • The EIR Addendum was considered and approved by the Board at the April 18 Board meeting.
  • The Program Management team continues to coordinate easement and Right of Way agreements with affected landowners.
  • SRWA finalized discussions with Modesto Irrigation District (MID) and is now moving forward with the preparation of a joint Watershed Sanitary Survey.

April 2019

  • Addenda #2, #3 and #4 for the Design Build RFP were issued.  The Program Management team also provided written responses to all questions raised during the Initial Design Concept meetings, and subsequent requests for clarification and/or more information.
  • The Program Management team continues to evaluate and aggressively pursue additional potential Project grant funding opportunities.
  • Wet Well construction activities continue. The very wet March weather resulted in some slowdown of construction activity, however in spite of these challenges, “soil freezing” was completed and excavation activities have commenced.
  • SRWA continues to work on the EIR Addendum, which is anticipated to be considered by the Board in April.
  • The Program Management team continues to coordinate easement and Right of Way agreements with affected landowners.