Project Updates

July 2019

  • The TAC and Program Management team continued review of the submitted proposals from the Design-Build Teams, and, in certain cases, requested follow-up clarifications and additional information.
  • The Program Management team continues to evaluate and pursue additional potential Project grant funding opportunities. Currently the PM team is assisting in preparing the pre-application package for an IRWM Prop 1 Grant Fund.
  • The SRWA has also just received a WaterSMART grant from the Bureau of Reclamation.
  • Wet Well construction activities continue with the bottom slab and portions of the lower walls formed and concrete poured, the structure is now starting to raise up out of the excavation.
  • The Program Management team continued to work on the SRF Technical and Financial application packages.
  • Coordination efforts for Right-of-Way acquisition continues.

June 2019

  • The TAC and Program Management team received and began review of the proposals submitted by each DB Team for SRWA’s Project.
  • The TAC and Program Management team also conducted interviews with each DB team, and continued review of the submitted proposals.
  • The Program Management team continues to evaluate and pursue additional potential Project grant funding opportunities.
  • Wet Well construction activities continue. Now that excavation is complete, construction work is focused on the construction of the Settling Basin and Wet Well walls.
  • The Program Management team continued to work on the SRF Technical and Financial application packages.